Power Line Tower Assessment
A cement plant customer is planning to add equipment that will require new electrical cables for power, which will be supported by existing towers. ZAP provided an analysis of the existing structures based on visual observations of condition and load capacity calculations based on drawings, cable tensions, and an existing geotechnical report. We were able to confirm how many cables and in what configuration they could be added to the existing towers without modification to the steel or foundations.