Engineering &
Construction Services, Inc.

Cement, Mining, and Minerals

end of project

Quicklime Screen

Design & Engineering of New Quicklime Screening System ZAP provided engineering and design support services (Mechanical / Structural) for a Quicklime production line replacement of a vibratory screen supported by structural steel. ZAP developed an analytical model of the main tower structure and a catwalk to check for the new static and dynamic forces associated […]

Fly Ash Terminal

ZAP Engineering & Construction Services, Inc. designed a greenfield fly ash terminal on an existing rail line. A new spur added for a new rail unloading pit. Fly ash unloaded at the rail pit was pneumatically conveyed from 2 convey pods to 1 of 3 storage structures. A single truck unloading station was added to pneumatically convey silos.  

img 2846

Fly Ash Separation Facility

Fly Ash Separation Facility EPCM ZAP performed detail engineering, procurement and construction management for a fly ash processing facility utilizing electrostatic separation technology. This brownfield facility included integration of the existing power plant, fly ash separation technology, and balance of plant materials handling equipment.  Process Detail: The existing fly ash silos were altered for the […]

img 5563 3

Plant Expansion

Plant Expansion ZAP was selected for detailed engineering of a new grinding circuit that has significantly increased production capacity at an existing mineral processing plant.  The project included supporting the customer through purchase of pre-owned as well as new equipment and providing the arrangement, equipment sizing, structure, building design, power, instrumentation, drainage and much more.  […]

Tower

Preheater Evaluation

Preheater Evaluation A cement plant was seeking to upgrade the size of the cyclones in their Preheater Tower which was going to modify both the framing geometry and maximum expected gravity and seismic loads on the tower.  A structural & construction evaluation was required to provide a total installed cost and schedule estimates for their […]

Tdf Electrical And Instrumentation

Tire Derived Fuels – Electrical & Instrumentation Eng

TDF Electrical and Instrumentation A cement plant improving the efficiency of their alternate fuel sources requested that ZAP provide electrical and instrumentation design to support the integration of equipment packages into a single material handling system.  The new system would allow for the delivery of whole tires that would be shredded prior to being used […]

Monorail Update

Monorail Update

Monorail Update ZAP provided structural engineering and design to support the client in their effort to provide a turn-key solution for a monorails installed in a hazardous reagent building located on a gold concentrate facility in Colorado.  ZAP completed a site visit to visualize each of the spaces and confirm the end-user’s intent and as-built […]

Soda Ash Loud Out

Soda Ash Load-Out

ZAP completed the engineering and design to modify an existing truck loadout system fed from a storage dome and from the F&I silo to meet Food Safety Modernization Act (FSMA) regulations.

Cement Plant Preheater Tower Retrofit

ZAP was contracted to make a structural analysis of an existing four stage concrete preheater tower at a cement plant. Engineering services included developing a design basis and determining what load cases would be applied to the tower.

Roof Access

Roof Access Platform

Plant maintenance requested improved access to a large duct’s slide gate above the roof level. A complex geometry was required to provide a platform that was supported by exterior building framing to avoid placing any load on existing roof trusses and yet account for operation of an adjacent roof hatch and maintain access to the slide gate components.

Power Line

Power Line Tower Assessment

A cement plant customer is planning to add equipment that will require new electrical cables for power, which will be supported by existing towers.

Kiln Support Saddle

During a plant outage, a cement customer found that their kiln lifting beam (or saddle) was buckling due to the compression forces between the kiln and the hydraulic cylinders used to lift the kiln off its trunnion rollers.

Dome

Dome Withdrawal Conversion

ZAP was contracted to modify an existing dome withdrawal system and convert the reclaim system from a mechanical auger to an aerated floor.

Cement & Slag Import Terminal

ZAP provided preliminary engineering and design for a cement and granulated blast furnace slag import and distribution terminal.

Meet the Team. (720) 529-4430

Call or send us your scope and we’ll assemble the team of experts who will help you successfully execute your project.

Schedule a meeting

ZAP ECS Logo

Excellence in Execution

Latest news and updates from around the company.

See All News