Colorado Crude Storage Terminal Expansion Cost Estimate
ZAP was contracted to complete a total installed cost estimate for the addition of two crude oil storage tanks and associated equipment required for metering at an existing crude oil terminal. ZAP completed initial design and solicited quotes from multiple vendors for equipment costs on the crude oil storage tanks, charge pumps, the inlet check meter skid, Coriolis meters, valves, and various instruments. ZAP’s extensive experience in oil and gas construction allowed for an accurate estimate of construction and installation costs.