Cement and Slag Import Terminal
ZAP provided preliminary engineering and design for a cement and granulated blast furnace slag import and distribution terminal. The project included three 20,000 ton import silos and two 5,000 ton silos for barge loading distribution operations. Preliminary design included interface with existing terminal equipment and structures, layout of storage and conveying equipment, maintenance access planning, and structural design. Project deliverables included a total installed cost estimate, preliminary layout, and structural drawings.